Landsvirkjun

Organic Rankine Cycle Geothermal Project

The 7.5 MWe Tuzla ORC geothermal power project comprised of geothermal wells, a steam gathering system, a power plant and a re-injection system. The services included supervision of drilling works and supervision of geothermal production and re-injection wells, well testing, conceptual design of steam gathering system, separator system and re-injection system.

Geothermal
Project type
Tuzla, Turkey
Location
7.5 MW
Capacity
2009
Completed
Landsvirkjun Power Ltd.

Haaleitisbraut 68
103 Reykjavík • Iceland

Parent company: Landsvirkjun
SSN: 450307-2380

Tel. +354 515 8900
Fax +354 515 8905
info@lvpower.com

Certifications
vottun

© 2020 All rights reserved